49 FERNRIDGE AVE VALLEY PARK MO
Updated Progress
05/06/25
The renovation is progressing with the goal of having the property ready for market listing within the next 2 to 3 weeks. An updated set of photos will be sent to Ralf by Monday, May 13th, to reflect the latest progress. A more detailed update will also be provided on that date to ensure continued alignment with the project timeline.
03/26/25
Great progress on the rehab! The drywall is complete, cabinetry is being installed, and electrical work is wrapped up. Another draw has just been completed, keeping everything on track. No pending permits or inspections, and with the current pace, completion is expected within the next month. The next big step is getting it listed on the market! Updated photos will be shared over the weekend.
02/27/25
The property rehab has made progress with the completion of the roof, windows, and framing. There are no pending permits or inspections required to move forward. The estimated timeframe for completion is uncertain at this stage, as the next phase depends on the arrival of funding. The draw has been submitted, and work will proceed once the funds are received. An update will be provided next month.
Basement
1st Month
SUPPORTING DOCUMENTS
STATEMENT OF WORK
PDF Loading...
SIGNED PRELIM TERM
PDF Loading...
PRELIM TERM SHEET
PDF Loading...
EXPERIENCE WORKSHEET
PDF Loading...
DEAL ANALYSIS CALCULATOR
PDF Loading...