916 N FALLON ST
Updated Progress
05/15/25
04/28/25
The progress was briefly paused over the past few weeks due to the contractor’s hospitalization. Work officially resumed today, 04/28/25, and the team is now being organized to continue with the rehab. A follow-up call next week will help monitor the progress and ensure everything stays on track.
03/19/25
The rehab is nearing the finish line, with full completion set for Monday next week. Just one final step remains—an electrical inspection, currently on hold as the last batch of materials arrives. Everything else is in place, making this project almost ready for the market. Soon, it’ll be time for the big moment—listing the property! Photos will be shared with the PML shortly to capture the progress.
02/20/25
The property rehab is currently 65% complete, with major milestones achieved, including the roof, drywall, plumbing, HVAC, and framing. No issues or delays have been encountered at this time. The project is on track to be fully completed within the next two weeks, while remaining within budget. Photos can be provided upon request.
01/16/25
The project is progressing well with several key tasks completed, including demolition, roofing, drywall installation, painting, electrical work, rough plumbing, and painting of interior doors. The interior trim work is also in progress. The HVAC ductwork has been completed, and work will soon begin on replacing the unit in the basement. The bathroom is still being finished, and attention is now focused on the kitchen. Although there has been a slight delay due to the need for additional funds for cabinets, the project is still on track overall. The budget is being managed effectively, and there are no significant concerns. Photos of the property will be provided tomorrow for further sharing with the PML.