Updated Progress
05/14/25
Right now, the project is moving through the core systems phase—demo is complete, and electrical and plumbing are underway. There aren’t any permit issues holding things up, which helps keep the momentum going. The next step is drywall, and the target is to have everything wrapped up by the end of July. That timeline feels reasonable based on where things stand. They’ve already lined up a realtor and are planning to list once the work is done, which keeps things moving on the back end, too. As a backup plan, they’re also looking into a DSCR loan if needed. All in all, the project seems to be in a steady spot, with key tasks progressing and a clear path ahead toward completion.
05/02/25
Renovation progress is advancing steadily, with approximately 30% of the overall rehab completed to date. Demolition and site cleanup have been finalized, and the project has now moved into the electrical phase following preliminary work on mechanical, electrical, and plumbing (MEP) systems. Contractors have remained consistent and punctual, helping to maintain momentum and alignment with the project timeline. Budget adherence remains on track, with no overruns reported at this stage. While no delays have occurred to date, updated progress photos and a walkthrough video are scheduled to be provided next week to further illustrate the ongoing development. Overall, the project remains well-positioned for continued progress in the coming weeks.
04/01/25
Rehab is officially underway, and things are already moving! The early stages are all about getting everything prepped and ready for the big transformations ahead. No permits are needed, which makes the process smoother. The estimated timeframe for completion is about 90 days. The next big step is listing the property on the market. Photos will be sent soon to share with the PML, giving everyone a sneak peek at all the hard work being done.