5256 COLLINGWOOD RD

Updated Progress

09/23/25

Tiling and interior painting have been completed as planned, and the project itself is now 100% finished. The only work happening at this point is a few final touches in preparation for the listing photos, which will capture the completed rehab. With that in place, the property is set to go on the market right away. It’s a clean handoff stage, moving from construction and updates into the marketing phase, which signals strong momentum toward a successful sale.

The borrower is targeting to complete the project between August 29 and September 5. As of yesterday, the crew started tiling all bathrooms and the kitchen, along with painting the interior. The new bathroom is already done, hardwood floors are finished, exterior painting is complete, and Phase 1 of landscaping is in place.
 

While Phase 3 photos will be available later this week in preparation for the second draw.
 

09/24/2025

08/12/2025

Phase 1

Phase 2

SIGNED OA

PDF Loading...

SIGNED JV HHA PN & PG

PDF Loading...

RENOVATION ARV

PDF Loading...

SIGNED PRELIM TERM SHEET

PDF Loading...

DEAL ANALYSIS CALCULATOR

SCOPE OF WORK

SIGNED PRELIM TERM SHEET

PDF Loading...